Technical project of the new construction
bridge over the "Vit" river
.
A project has been prepared for a three-span bridge with different lengths and the various options.
Option 1 was selected by the Employer after phase 1 of the design and was fully developed. The project was prepared with full geodetic and geological surveys, as well as projects for environmental protection and safe working conditions during construction. The purpose of the project is to prepare an assessment of the condition of the existing bridge abutment and, if possible, to adapt it in the design of the new superstructure and substructure. The total length of the superstructure of the bridge is 63.00 m. The dimensions consist of a roadway – 8.00 m and sidewalks 2×2.00 m.