Preliminary design for bypasses
Ring Road from Ralevitsa Str. to Lyulin Motorway of the Sofia
.
The project concerns the design of two road bridges.
Total length of the bridge 1329.00 m with a width of 27.50 m (2 lanes 10.50 m + dividing strip 3.00 m + 2 pavements 1.75 m).
Total length of the ramps 153.50 m with a width of 8.50 m (1 lane 6.00 m + dividing strip 0.75 m m + pavement 1.75 m).
The structure of the bridge consists of 57 spans of different lengths, divided into 13 separate sections:
Total length of the bridge 200.00 m with a width of 27.50 m (2 lanes 10.50 m + dividing strip 3.00 m + 2 pavements 1.75 m).
The construction of the bridge consists two separate facilities, one for each direction of the road. It is divided into 4 sections with reinforced concrete superstructure with a length of 100 m, two for each direction. Each of the sections has 3 spans (2 end spans of 30.00 m and the middle span of 40 m).
Preparation of a preliminary design project for the construction part of the project from km 52 + 363.42 to km 53 + 692.42 and from km 54 + 360 to km 54 + 560 of the Sofia ring road from Ralevitsa Str. to Lyulin motorway; Sofia city